Fixed Date Planning
We need it on this date. How much can we have by then? There are there steps here : 1. Determine how many iterations you have 2. Estimate velocity as a range 3. Use that "range x the number of iterations" to partition the backlog into Will Have, Might Have, and Won't Have. In general you want to balance for two types of risk. Always determine the range even if you need to communicate a single value. So you can show the truth about the project by sharing the math above. Then f