I want this much. When can I get it?

We create a fixed-scope plan in response to the question of “when will all of this be done?”


There are 3 steps here

  1. Sum the product backlog items

  2. Estimate velocity as a range

  3. Use the sum of the backlog divided by the vel...

September 11, 2015


Someone said : “I want all of this by that date”

This type of project is generally considered the hardest to manage.

There are two type of this kind of project.

1. You are given no choice. This refers to the cases when someone has literally dictated both date and scope....

September 2, 2015

We need it on this date. How much can we have by then?

There are there steps here :

1. Determine how many iterations you have

2. Estimate velocity as a range

3. Use that "range x the number of iterations" to partition the backlog into Will Have, Might Have, and Won't Have.

...