I want this much. When can I get it?

We create a fixed-scope plan in response to the question of “when will all of this be done?”


There are 3 steps here

  1. Sum the product backlog items

  2. Estimate velocity as a range

  3. Use the sum of the backlog divided by the vel...

September 11, 2015


Someone said : “I want all of this by that date”

This type of project is generally considered the hardest to manage.

There are two type of this kind of project.

1. You are given no choice. This refers to the cases when someone has literally dictated both date and scope....

August 20, 2015

Lets assume that you have 26+ past iterations to calculate velocity and there are 5 iterations left to finish product backlog. So how many backlog items can you do until the end of the project?

Velocity Calculation Steps


- As per the table below you should throw out 8 b...