September 9, 2016

I want this much. When can I get it?

We create a fixed-scope plan in response to the question of “when will all of this be done?”


There are 3 steps here

  1. Sum the product backlog items

  2. Estimate velocity as a range

  3. Use the sum of the backlog divided by the vel...

September 2, 2015

We need it on this date. How much can we have by then?

There are there steps here :

1. Determine how many iterations you have

2. Estimate velocity as a range

3. Use that "range x the number of iterations" to partition the backlog into Will Have, Might Have, and Won't Have.

...

August 11, 2015

Why planning poker works?


Here are some reasons for playing planning poker:

  1. The people doing the work do the estimates

  2. Estimator have to justify estimates

  3. Most estimates are within one order of magnitude (most of them between 1 and 10, actually it should b...